How do you move a production line to the U.S.?
The short answer: Plan it as a project, working back from the date your customer needs supply from the new site. From there, set the timeline for dismantling, shipping, installation and ramp-up. Build safety stock for the transition, and move the know-how together with the machines.
What are the stages?
- Plan: what moves, what you buy new, and in what order.
- Prepare the site: power, utilities and floor ready before the equipment arrives.
- Safety stock: produce ahead to cover the transition.
- Dismantle, crate and ship with a specialist in industrial equipment. A licensed customs broker handles the customs side.
- Install and ramp up, including customer approval of product from the new site where required.
What mistakes are most common?
- The site is not ready when the equipment arrives.
- Safety stock is too small.
- The know-how stays behind: machines move without the people who know how to run them.
- Forgetting that the customer may need to approve product from the new site.
How Kay Group helps
We help plan and manage the move: timeline, site readiness, supplier coordination, ramp-up and knowledge transfer, so your team can keep running the business. Soft Landing for manufacturers
More questions
Should we move existing machines or buy new ones in the U.S.?
It depends on the age of the equipment, the cost of moving it, lead times for new equipment, and service and spare parts availability in the U.S. Often the answer combines both.
Official sources
Kay Group Inc. does not provide legal, tax, immigration or regulatory advice. This page describes the topic in general terms; decisions on these subjects belong with your attorney, accountant and licensed advisors.
By Hadas Kasher, co-founder of Kay Group Inc. Published November 15, 2026.